New ADU construction — detached or attached. Includes LB-specific ADU permitting process.
How to build an ADU in Long Beach. This playbook breaks the full accessory dwelling unit process into 49 steps — planning, design, Long Beach permitting, utility connections, construction, and inspections — each with typical durations, costs, and who to call.
This playbook is a starting point — add, remove, or reorder any step when you start your project.
ADU Feasibility Assessment
Verify property eligibility — zoning, lot size, setbacks, existing structures, utility capacity.
Site Survey & Lot Analysis
Professional survey to confirm lot dimensions, existing structure footprint, setback distances, and utility locations.
Utility Capacity Check
Confirm water, sewer, gas, and electrical capacity for a new unit. Check if panel upgrade is needed.
Obtain ADU Contractor Bids
Get 2–3 bids from ADU-experienced contractors. Verify CSLB license and ADU-specific portfolio.
Hire ADU Architect
Engage architect experienced with Long Beach ADU requirements for design and permit drawings.
Architectural Plans & Site Plan
Floor plan, elevations, site plan showing ADU placement and setbacks, foundation plan.
Structural Engineering
Structural calculations and details for foundation, shear walls, and roof framing.
Title 24 Energy Report
California energy compliance report (required for all new construction).
Submit ADU Permit Application
Submit building permit application, plans, and all required documents to Long Beach Development Services.
Plan Check Review
City reviews plans for code compliance. May require corrections and resubmittal.
Pay Permit Fees & Pull Permit
Pay building, electrical, plumbing, and mechanical permit fees. Receive permit card.
Post Permit Card on Site
Display permit card and approved plans at the job site per LB requirements.
Request Temporary Power (SCE)
Arrange temporary electrical service for construction if needed.
Utility Trench Design & LBWD Coordination
For detached ADU: plan new water/sewer connections. Get LBWD approval for connection point.
Order Materials & Schedule Subcontractors
Order lumber package, windows, roofing materials. Lock in plumbing, electrical, HVAC subs.
Set Up Job Site (Fencing, Dumpster, Portable Toilet)
Secure the job site with temporary fencing. Order dumpster and portable toilet.
Pre-Construction Inspection
Initial site inspection before any work begins. Inspector confirms permit is posted and plans are on site.
Demolition & Site Prep
Remove any existing structures in ADU footprint. Grade the site. Mark utilities.
Underground Plumbing
Install underground drain/waste/vent lines and water supply to the ADU before foundation pour.
Underground Electrical
Run electrical conduit underground from main panel to ADU location.
Rebar & Hold Downs
Install rebar grid, hold-down bolts, and anchor bolts per structural plans before concrete pour.
Foundation (Slab or Raised)
Pour concrete slab or construct raised foundation per structural drawings.
Foundation Inspection
Required inspection before concrete pour — inspector must approve rebar and forms.
Framing
Erect wall framing, roof framing, and sheathing per approved plans.
Shear Walls
Install shear wall panels and nailing per structural plans for lateral bracing.
Framing Inspection
Inspector reviews all framing, shear walls, headers, and hardware before any walls are closed.
Rough Plumbing
Install all drain/waste/vent lines, water supply lines, and connections to new meters.
Rough Electrical
Run all electrical circuits, install panel, and rough in all boxes per plans.
Rough HVAC
Install ductwork, mini-split line sets, and ventilation per mechanical plans.
Rough MEP Inspections
Inspections for rough plumbing, electrical, and mechanical before walls close.
Insulation
Install batt insulation in walls and ceiling per Title 24 requirements.
Insulation Inspection
Inspector confirms insulation meets Title 24 before drywall is installed.
Wire Mesh & Lath
Install wire mesh/metal lath on exterior walls in preparation for stucco.
Stucco — Scratch Coat
Apply first coat of stucco (scratch coat) over wire mesh. Must cure before brown coat.
Stucco — Color Coat
Apply final color coat of stucco. Choose texture and color to match or complement main house.
Drywall Hang
Hang drywall sheets on all interior walls and ceiling. Fire-rated assemblies at shared walls.
Mud & Tape
Tape joints, apply mud (joint compound), sand smooth. Multiple coats for level 4 finish.
Finish Plumbing & Electrical
Install fixtures, outlets, switches, panels, water heater, and all finish connections.
Flooring, Cabinets & Countertops
Install LVP or tile flooring, kitchen cabinets, bathroom vanity, and countertops.
Interior Paint
Paint all walls, ceilings, and trim.
Exterior Siding, Windows & Roofing
Install windows, exterior siding/stucco, and roofing per approved plans.
Utility Meter Installations (SCE, SoCalGas, LBWD)
Coordinate final meter installations with all utilities.
Final Building Inspection
Comprehensive final inspection covering all trades and code compliance.
Final Electrical Inspection
Electrical final — panel, fixtures, outlets, EV charger rough-in verification.
Final Plumbing & Mechanical Inspection
Plumbing final — fixtures, water heater, sewer connection. Mechanical final — mini-split installation.
Certificate of Occupancy (CO)
Final sign-off and issuance of Certificate of Occupancy. ADU is now legally habitable.
Final Cleaning & Punch List
Professional post-construction clean. Walk and fix all remaining items.
Utility Account Setup for Tenant
Register separate utility accounts for the ADU. Get account numbers ready for tenant.
Final Project Accounting & Lien Releases
Reconcile all costs, collect final payments, and obtain lien releases from all contractors.
Phases
Planning
4 steps · ~31d
Design
4 steps · ~47d
Permitting
4 steps · ~35d
Pre-Build
4 steps · ~40d
Construction
26 steps · ~106d
Inspections
4 steps · ~14d
Completion
3 steps · ~15d
Quick Stats
Every template is a free step-by-step checklist with typical durations, costs, and Long Beach city contacts. Sign up free to turn any of them into a live build tracker.
Full Rehab
Complete 45-step full home rehab playbook for Long Beach: permits, demolition, framing, electrical, plumbing, inspections, and finish work — with typical costs and a ~253-day timeline.
SB-9 Lot Split
The California SB-9 lot split process in 32 steps: entitlement, survey, design, permitting, and dual-unit construction — with typical costs and a ~271-day timeline for Long Beach lots.
Cosmetic Flip
Fast 17-step cosmetic flip checklist — paint, flooring, kitchen, and bathroom refresh — optimized for 30-day turnarounds in Long Beach, with typical costs and a ~32-day timeline.